ProjectNew Saint Paul's Hospital
Address1002 Station Street Vancouver BC
Site SuperintendentJoma Abella
General ContractorPCL Constructors Westcoast Inc.
13911 Wireless Way Suite 310 Richmond BC V6V 3B9 Canada
Comments

Structural steel for the New St Paul's Hospital. Beams and Columns.

Sideros Ironworks Ltd. is certified to CSA Standard W47.1 “Certification of companies for fusion welding of steel” in Division 2 and, therefore, does meet the requirements of CSA S16 Clause 24.3 which is referenced in the National & Provincial Building Codes Section 4.3.4.1.

NBCC Section 4.3.4.1: "Building and their structural members made of structural steel shall conform to CSA S16 “Design of Steel Structures.”

CSA S16 Clause 24.3: “Fabricators and erectors responsible for welding structures fabricated or erected under this Standard shall meet the requirements of CSA W47.1, CSA W55.3 or both, as applicable in Division 1 or Division 2. Part of the work may be sublet to a Division 3 fabricator or erector; however, the Division 1 or Division 2 fabricator or erector shall retain responsibility for the sublet work.”

Site ContactJoma Abella
CWB RepresentativeAdam Ferns
Date2025-10-30